Ronkonkoma Hub Aerial Photos July 2018
Building 1
Wood Framing installation is continuing up on the 4th floor.
Roof Trusses are moving forward at the South side.
Mechanical, Electrical, Plumbing rough in is underway on the 2nd and 3rd floor.

Building 2
Wood Framing installation is complete.
Roof Trusses are moving forward and in progress on 65% of the building.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is complete at the first floor and progressing up to the 2nd floor.

Building 3
Underground Plumbing is 75% complete
Underground Electrical Rough is 50% complete

Building 4
Foundation is 90% complete
Elevator shaft construction is underway

Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in October, 2018.

Building 6
Siding is complete.
All interior rough in is complete awaiting final inspection
Insulation has been loaded to side

Sitework
Curb formwork and installation has started
Starting to set building site to final subgrade
Pump station Wet Well slab and footings have been poured and wall formwork is commencing