IMG_0319

IMG_0319

For removal of flat spots and kinks out come the slewing jacks. Here a flat spot in the curve is adjusted. Winchcombe platform 1, 18/02/2012

Anyone can see this photo All rights reserved

Uploaded on Feb 19, 2012

0 comments

IMG_0314

IMG_0314

Ballast has just been dropped from the dogfish, the gang spread ballast by shovel, Winchcombe 18/02/2012

Anyone can see this photo All rights reserved

Uploaded on Feb 19, 2012

0 comments

IMG_0312

IMG_0312

The gang stand well clear of Mr. D. Angerous as he sets too adjusting the sleeper ends with chain saw to allow barrow crossing to be refitted at Winchcombe, 18/02/2012

Anyone can see this photo All rights reserved

Uploaded on Feb 19, 2012

0 comments

IMG_0320

IMG_0320

Platform 1 at Winchcombe relayed, re-ballasted and re-aligned, job finished! 18/02/2012

Anyone can see this photo All rights reserved

Uploaded on Feb 19, 2012

0 comments

IMG_0296

IMG_0296

More ballast is required to finish off the initial pass to allow lifting and packing to take place. At minus 7deg C suprisingly the ballast is not too lumpy and is able to be shovelled. Winchcombe 11/02/2012

Anyone can see this photo All rights reserved

Uploaded on Feb 12, 2012

0 comments